• Dublin Elementary School Water Conservation & Management Project

    Dublin Elementary WCMP
     

    Project Team:

    Architect:  HKIT Architects
    Project Manager:  Craig Lemos
     
    Contractor:
    Increment 1:  Bay Valley Construction, Inc.
    Increment 2:  Bay Valley Construction, Inc.
     
    Project Scope: 

    Increment 1 project scope includes renovation of campus playfields, construction of a fitness loop, installation of two new playground structures, renovation of an existing playground with a recycled rubber surfacing, utility installation, construction of a school garden area, removal and replacement of the southern driveway entrance and a portion of the sidewalks in front of the school, landscaping and irrigation, and conversion of the campus irrigation to reclaimed water. Special Education Preschool scope includes a new playground area with a play apparatus. Increment 2 work includes construction of a 30’ x 28’ garden shed and 44’ x 36’ lunch shelter to complete the Water Conservation and Management Project.

     
    Construction Increment 1:
    Start:  Summer 2015
    Completion:  Spring 2016 
     
    Construction Increment 2:
    Start:  Summer 2016 
    Completion:  Fall 2016